Teri developed a PERT chart that showed her the longest line of activities where a delay in any of the activities would cause a delay in her entire…

Teri developed a PERT chart that showed her the longest line of activities where a delay in any of the activities would cause a delay in her entire project. Teri was using the _____ method.

activity path

critical path