Teri developed a PERT chart that showed her the longest line of activities where a delay in any of the activities would cause a delay in her entire…
Teri developed a PERT chart that showed her the longest line of activities where a delay in any of the activities would cause a delay in her entire project. Teri was using the _____ method.
activity path
critical path
Save your time - order a paper!
Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines
Order Paper Nowlongest path
Gantt path