I have a question with Project Management – Wiley Pathways – Chapter 13 – Applying This Chapter – Question number 2.
I have a question with Project Management – Wiley Pathways – Chapter 13 – Applying This Chapter – Question number 2. In her project’s risk management plans, Lisa lists several risks including “the project is too large,” “tasks are under-budgeted,” and “not enough workers.” What can Lisa do to improve the effectiveness of the risks she’s identified? How might she reword her risk identification statements greater specificity?